Project Update

First floor walls are nearly complete.
Only interior walls in a few unit are remaining.
Trusses scheduled to be delivered Wednesday afternoon or Thursday morning.




Wednesday, December 21, 2016

Exterior Walls

About 1/3 of the exterior walls are set. Hoping to have all 1st floor walls set by the end of the week.





Monday, December 12, 2016

Framing

The pre-cast deck has been cleared after all the snow. Carpenters have sanpped all the lines on the deck. Despite the cooler temperatures, the sun was able to dry the deck off.



Tuesday, November 29, 2016

Pre-cast

We will finish setting the last couple plank tomorrow morning and grout the pre-cast. We will also excavate the remaining footing and pour the footing and frost wall.



Tuesday, November 22, 2016

Saturday, November 19, 2016

Foundation & Pre-Cast

The foundation walls are set for the last pour Friday.
Also pre-cast columns are getting set.







Monday, November 14, 2016

Foundation Update

Walls are being formed for the elevator pit and the remainder of walls.






Friday, November 4, 2016

Foundation Update

The 2nd pour is complete and forms are being removed. Site storm water pipe is also being installed.



Thursday, October 20, 2016

Foundation

The foundation is starting to get formed up. We will pour the first 1/3 of the wall on Monday. 


Thursday, July 28, 2016

Wednesday, July 13, 2016