Project Update
First floor walls are nearly complete.
Only interior walls in a few unit are remaining.
Trusses scheduled to be delivered Wednesday afternoon or Thursday morning.
Wednesday, December 21, 2016
Exterior Walls
About 1/3 of the exterior walls are set. Hoping to have all 1st floor walls set by the end of the week.
Monday, December 12, 2016
Framing
The pre-cast deck has been cleared after all the snow. Carpenters have sanpped all the lines on the deck. Despite the cooler temperatures, the sun was able to dry the deck off.
Tuesday, November 29, 2016
Pre-cast
We will finish setting the last couple plank tomorrow morning and grout the pre-cast. We will also excavate the remaining footing and pour the footing and frost wall.
Tuesday, November 22, 2016
Saturday, November 19, 2016
Monday, November 14, 2016
Friday, November 4, 2016
Foundation Update
The 2nd pour is complete and forms are being removed. Site storm water pipe is also being installed.
Thursday, October 20, 2016
Thursday, July 28, 2016
Wednesday, July 20, 2016
Monday, July 18, 2016
Wednesday, July 13, 2016