Tuesday, November 29, 2016

Pre-cast

We will finish setting the last couple plank tomorrow morning and grout the pre-cast. We will also excavate the remaining footing and pour the footing and frost wall.



Tuesday, November 22, 2016

Saturday, November 19, 2016

Foundation & Pre-Cast

The foundation walls are set for the last pour Friday.
Also pre-cast columns are getting set.







Monday, November 14, 2016

Foundation Update

Walls are being formed for the elevator pit and the remainder of walls.






Friday, November 4, 2016

Foundation Update

The 2nd pour is complete and forms are being removed. Site storm water pipe is also being installed.